Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/08/2006 | GRADING - FINAL | Approved | ||
| 11/29/2005 | GRADING - FINAL | Denied | 1. SUBMIT A REVISED GRADING PLAN TO THE CITY OF TUCSON DEVELOPMENT SERVICES, ENGINEERING AND ZONING DIVISIONS FOR REVIEW AND APPROVAL. SHOW AS-BUILT ELEVATIONS FOR MODULAR BUILDINGS AND MODIFICATIONS TO THE 6' LOW FLOW PIPES IN THE RETENTION BASIN AND THE SIDEWALK SCUPPER IN THE RIGHT OF WAY. 2. PROVIDE AN ENGINEER'S CERTIFICATION LETTER FOR THE RETENTION/DETENTION BASIN THAT INCLUDES INFILTRATION/PERCOLATION INFORMATION. 3. PROVIDE A 5' PAVED ACCESS WALKWAY TO CONNECT TO THE NEW CONCRETE SIDEWALK INT THE R.O.W. AT THE SOUTHEAST CORNER OF THE PROPERTY. SEE KEYNOTE #35 PAGE C.I.O.. |
|
| 11/18/2005 | GRADING - FINAL | Denied | 1. PROVIDE APPROVED PLANS FOR MODULAR BLDG. 2. PROVIDE END CAPS AND 4" ORIFICE PLATE ON R/D BASIN LOW FLOW BLEED PIPES. 3. REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 4. PROVIDE AN ENGINEERS CERTIFICATION LETTER FOR THE R/D BASIN. 5. PROVIDE A 5' PAVED ACCESS WALKWAY AT SOUTHEAST CORNER OF SITE (SEE KEYNOTE #35). |
|
| 09/01/2005 | GRADING - FINAL | Denied | 1. COMPLETE MODULAR BLDG. INSTALLATION AND PROVIDE APPROVED PLANS. 2. PROVIDE END CAPS AND 4" ORIFICE PLATE ON R/D BASIN LOW FLOW BLEED PIPES. 3. PROVIDE CONCRETE WHEEL STOPS IN THE PARKING LOT 4. REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 5. PROVIDE ROCK RIP-RAP OVER FILTER FABRIC AT DRAINAGE OUTLETS ON THE NORTH DRIVEWAY DISCHARGES. 6. PROVIDE AN ENGINEERS CERTIFICATION LETTER FOR THE R/D BASIN. |
|
| 08/18/2005 | GRADING - FINAL | Denied | 1. COMPLETE 10' EMERGENCY SPILLWAY AT SOUTHWEST END OF RETENTION/DETENTION BASIN AND VERIFY MAXIMUM 2' DEPTH. 2. PROVIDE (2) 6" IRON BLEED PIPES FOR RETENTION BASIN, PIPE MUST STOP AT PROPERTY LINE AND TYPE I OR II SCUPPERS INSTALLED AT CURB. 3. RIP RAP FULL 10' INLET SPILLWAY TO TOP OF BANK ANT THE R/D BASIN INLET. 4. COMPLETE ALL STRIPING AND WHEEL STOP INSTALLATION. 5. COMPLETE SIDEWALK AND HANDICAP RAMPS AT THE DRIVEWAY ENTRANCE AT TANQUE VERDE ROAD. 6. PROVIDE C.O.T. STAMPED AND APPROVED PLANS FOR MODIFICATIONS TO THE PARKING LOT. 7. PROVIDE THE 1ST ANNUAL LETTER FROM THE ENGINEER, CERTIFYING THAT THE R/D BASIN IS CONSTRUCTED AND OPERATING PER THE DESIGN CRITERIA. |
|
| 08/17/2005 | GRADING - FINAL | Cancelled | RESCHEDULED FOR 8-18-05 |