Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T04BU01737


Addresses:

5864 S STEWART BL


Inspection Status: Continued

Inspection History: GRADING - FINAL

Permit Number - T04BU01737

Inspection Description - GRADING - FINAL

Inspection Status - Continued

Date Description Inspector Results Comments
05/01/2012 GRADING - FINAL Continued WALKED AND PHOTOGRAPHED THE SITE TO SEE WHAT IS STILL NEEDED FOR THIS AREA TO BE COMPLETED. THIS SITE STILL NEEDS WORK TO BE COMPLETED, BUT MOST OF IT WILL BE COMPLETED WITH EACH INDIVIDUAL LOT. MOST OF THE COMMON AREAS HAVE BEEN COMPLETED AT THIS TIME BUT THE DENTENION BASIN IS STILL IN A ROUGH GRADE STATE AT THIS TIME. THIS WORK WILL HAVE TO BE COMPLETED BEFORE THIS SITE REACHES THE 75% RELEASE OF THE LOTS.
02/18/2009 GRADING - FINAL Correction Required Issued Correction Notice. Contractor needs to:
1- Restore all SWPPP controls to working condition or stabilize all areas of site un-worked. Per AZ permit. Contractor has 30 days to address. Non-complaince will result in Notice of Violation or Citation.
01/29/2009 GRADING - FINAL Partial Approval Basin not holding water. Contractor still needs to address issue from inspection on 8/19/08.
08/19/2008 GRADING - FINAL Correction Required Contractor installed drainage channel in basin. Engineer needs to provide revised drawing for approval at 201 N. Stone. Contractor still needs to call in final inspection and stabilize site.
08/05/2008 GRADING - FINAL Correction Required Contractor started excavating for drainage channel in basin. Basin holding water for more then 24 hours. 4' wide by 3.5 deep runs from the northwest corner to the southeast corner.
08/04/2008 GRADING - FINAL Correction Required Spoke to Jim B. in regards to basin. Jim said contractor was going to start work on 8/5/08 to try and get basin to perc.
07/21/2008 GRADING - FINAL Correction Required Issued NOV. Contractor has 20 days to correct problems with basin (no swppp controls, holding water longer then 24 hours). If items are not addressed will issue stop work order for site. Spoke to Jim Brooks in regards to.
07/11/2008 GRADING - FINAL Correction Required Spoke to Jim Brooks in regards to basin holding water and site needs to be stabilized.
09/06/2006 GRADING - FINAL Correction Required Spoke to Jim Brooks with La Causa Construction (Office 882-0018/Cell 631-3616) in regards to complaint called in over the week end. I explained to the basin needs to be put back in working order or he need to keep it pumped out. Per Dave Roberts any more problems with the basin will result in a NOV being issued.
08/01/2006 GRADING - FINAL Correction Required Basin holding water.
09/07/2005 GRADING - FINAL Correction Required Eagle Rock is grading site with no stormwater controls installed. Talked to Eric with Eagle Rock who had the SWPPP plan and grading plan, I explained to Eric that the stormwater controls should be installed before grading takes place. Eric said he was going to call his supervisor and have him call me. I also explained to Eric that Eagle Rock should have called in for a pre-con meeting before grading started. Left my card with Eric.