Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2005 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 12/20/2004 | STORMWATER FOLLOW-UP INSP | Correction Required | STABILIZE THE AREA SOUTH OF THIS PROJECT OR PROVIDE APPRORIATE SEDIMENT AND EROSION CONTROLS. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS FROM THE STORMWATER DRAINAGE CHANNEL. |
|
| 07/15/2004 | STORMWATER FOLLOW-UP INSP | Correction Required | 1. RESET SILT FENCE PER SWPPP DETAIL "A" OR MAKE MODIFICATIONS TO PROVIDE EROSION AND SEDIMENT CONTROL ON THE NORTH PERIMETER. 2. STABILIZED CONSTRUCTION ENTRANCE REQUIRES MAINTENANCE. 3. PROVIDE A DESIGNATED CONCRETE WASHOUT AREA. 4. POST THE NOI AND INFORMATION REGARDING THE SWPPP PER AZPDES REGULATIONS ON PAGE 19 SEC. J. |