Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T03CM05695
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/24/2006 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
04/17/2006 | BUILDING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. YOU NEED A LISTED SYSTEM FOR YOUR BASEMENT WALL WHERE TOP IS NOT AGAINST CONCRETE BEAM. 2. SHEETROCK & FIRESTOP INSPECTION WAS NEVER CALLED FOR BASEMENT WALL AND PAINT NOW COVERS CRITICAL AREAS. 3. YOU NEED A LISTED DOOR ASSEMBLY AT OPENING. |
|
04/04/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* 2 HR WALL FRAME IN BASEMENT OK DON'T FORGET SMOKE SEALS ON 90 MINUTE DOORS |
|
02/16/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* BASEMENT DRESSING ROOM AREA WALKED THROUGH THIS IS A LIST OF DEFICIENCIES THAT COULD EXPAND AS MORE WORK IS LEFT TO BE DONE IN THIS AREA. THIS LIST IS IN ADDITION TO REQUEST FOR SEWER EJECTOR PIT SHOP DRAWINGS. 1. OPEN DATA BOX IN CEILING 2. ABS PIPE DIRECTLY (1") OVER LAMP BARS 3. EXPOSED DATA CABLES OVER SHOWER 4. EXPOSED FLEX CONDUIT AND NON WATER TIGHT ELECTRIC BOX OVER SHOWER 5. NO SMOKE SEALS/SWEEPS INSTALLED IN 2 HR DOORS TO ORCHESTRA PIT. 6. EMPTY NON WATER TIGHT J-BOX OVER SHOWER 7. NON WATERPROOF LIGHT FIXTURES IN SHOWER STALLS 8. FIRE STOP A) REMOVED IN CEILING B) MISSING IN OPEN DATA CONDUITS C) MISSING WHERE ADDED CONDUITS INSTALLED TO STAGE D) MISSING WHERE ADDED CONDUITS INSTALLED IN ORGAN PIPE ROOMS E) 1 HR SEPARATION NOT MAINTAINED AT STORAGE ROOM DOOR. 9. OPEN LAMP OUTLETS IN DRESSING ROOM YOU WILL ALSO NEED A COMPLETE ELECTRICAL INSPECTION SO WE MAY |
|
01/06/2006 | BUILDING - PROGRESS | Partial Approval | FIRESTOP DONE UNTIL ORGAN INSTALLED , AT THAT TIME I WILL REINSPECT ORGAN CHAMBERS I STILL NEED PLAN FOR STORAGE 3 HR SEPARATION OK TCO FOR SINGLE DAY SPECIAL EVENTS |
|
01/04/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* FIRE STOP: A. TOP FLOOR DONE B. MUD & TAPE SPRINKLER PIPE INSIDE MOP CLOSET BY MAIN FLOOR CONCESSION C. SODA LINES MAIN FLOOR D. AS DIRECTED DURING WALK THRU IN BASEMENT |
|
12/29/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* 1. FIRE STOP PROGRESS OK - BUT PLEASE KEEP IN MIND THAT THERE ARE MANY OTHER AREAS AND ISSUES CONCERNING FIRE SEPARATION AND PROTECTION. 2. ONE BIG ISSUE IS THAT 3 HR FLOOR CEILING ASSEMBLY BETWEEN STAGE RIGHT EXIT PASSAGE AND BASEMENT INCIDENTAL USE AREA IS INCOMPLETE. STRUCTURE IS PARTIALLY WOOD FRAME. |
|
12/28/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*FIRESTOP INCOMPLETE AT: 1) BASEMENT A) CEILING TO STAGE FROM ACTOR DRESSING ROOM SOUTH END/ B) NORTH END WHERE SPRINKLER PIPE REMOVED CEILING C) NORTH END AND NORTH DRESSING ROOM OPEN CONDUITS CEIL? D) HARDWATER ON RATED DOORS E) BEAM OVER ORCHESTRA PIT CENTER F) CEILING AT WEST END "SHAFT" G) BASEMENT LOUNGE MOP ROOM CEIL/ WALL JOINT. 2) MAIN FLOOR A) ELEC CONDUIT BANK INSIDE CHASE AT MEN'S ROOM FLOOR B) WEST WALL ?? SYSTEM WALL TO CEILING ABOVE WOMENS LAV'S C) WEST HALL INSULATED PIPES 3) TOP FLOOR A) ABOVE ??NTERING B) LOUNGE SIDE OF 3 HR WALL C) ABS BETWEEN MEN & WOMEN D) DUCT AS DISCUSSED |
|
12/27/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*INCOMPLETE FIRE SAFING FOLLOWS 1) MAIN FLOOR A) WEST WALL WOMENS ROOM @ CEILING B) WEST WALL CONCESSION TO STAIR WELL? C) 2 HR WALLS IN " SHAFTS" D) SPRINLER PIPE PENETRATION THROUGH CEILING SOUTH OF STAGE 2) TOP FLOOR A) JOINT SYSTEM CEILING TO 3 HR WALL B) PENETRATION EAST SIDE OF 3H WALL TO BAR C) ABS PENETRATIONS INTO ROOF/CIEL WOMENS ROOM BETWEEN M/W AND OVER LAV D) JOINT AND WALL SYSTEMS INSIDE " CHASE" NORTH SIDE OF BATHROOM GROUP E) FLOOR IN MOP CLOSET WEST END OF HALL F) WALL AND CEILING PENETRATION IN CATERING AREA G) 2 HR WALLS AT '' SHAFTS" 3) BASEMENT 1) CEILING TO STAGE FLOOR VARIOUS AREAS ACTORS DRESSING & RESTROOMS 2) UTILITY CLOSET CEILING OVER DUCT AT REAR. 3) ALL PENETRATIONS OF CEILING ABOVE BASEMENT BATHROOM GROUP |
|
12/23/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*FOR TCO I NEED FOLLOWING FIRESTOP COMPLETE FIRE DOORS COMPLETE ELECTRIC & PLUMBING ? FIRE TO APPROVE TCO ( MECH HAS ALREADY APPROVED TCO) I NEED TO SEE GENERAL LIGHTING THAT WILL BE PROVIDED |
|
12/22/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*USE THIS FOR FIRE STOP INSPECTION HYDRONIC PIPIE SUPPORT INSPECTIONS ( WELDING) EJECTOR PIT FOR SEWER |
|
12/21/2005 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* |