Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/05/2005 |
PLUMBING - FINAL |
|
Approved |
IVRS - Inspection :* 1) REVISED DRAWING ARE OK. 2) OK FOR C OF O |
| 06/28/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :* 1) REVISED & APPROVED PLANS ARE NOT READY FOR MY REVIEW |
| 04/20/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) BACKFLOW PREVENTERS HAVE BEEN TESTED & CERTIFIED FOR SPECIALTY KITCHEN 2) SHALL PROVIDE REVISED AND APPROVED PLANS ON RED LINES PRIOR TO FINAL |
| 04/18/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) PLBG FINAL IS OK FOR SPECIALTY RESTAURANT BLDG H. 2) SHALL PROVIDE TEST & CERTIFICATION TO ALL BACKFLOW REVERTERS PRIOR TO FINAL |
| 02/07/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 02/04/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) BACKFLOW PREVENTERS TEST AND CERTIFICATION HAVE BEEN COMPLETED. 2) STILL PENDING SPECIALTY KITCHEN TEST & CERT. |
| 02/03/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
1) NOT READY FOR INSPECTION |
| 01/20/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) PLBG FINAL BLDG H LEVEL 3 & Y ARE OK 2) PLBG FINAL BLDG G LEVEL P-2 SPA AREA LOCKED & TREATMENT RM AND JUICE BAR ARE OK 3) OK FOR TEMP C OF O |
| 01/18/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* LEVEL 3 SECTION G ROOMS ONLY OK. LEVEL 4 SECTION G ROOMS ONLY OK. LEVEL 2 SECTION H ROOMS ONLY OK. LEVEL P-1 FITTNESS AREA SECTION G REST ROOM 1 STOOL & 1 LAV OK . THESE AREAS OK FOR TEMP C. OF. |
| 01/14/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*PARTIAL APPROVAL-BATHROOM P-231 @ WEIGHT ROOM IS OK. |
| 01/12/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) BLDG LEVEL 3 GUEST ROM BATHROOMS ARE OK ENTIRE FLOOR 2) BDLG LEVEL `1 MENS & WOMENS RESTOOMS ARE OK ALL CORRECTIONS HAVE BEEN MADE FOR MEETING RESTROOMS. |
| 01/11/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :*NOT READY |
| 01/11/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) PLBS FINAL IS OK FOR BLDG D LEVEL 6 AND FOR BLDG LEVEL 2. 2) NOTE: BLDG G LEVEL 1 PUBLIC RESTROOMS MENS URINAL REQUIRES 15" MIN FROM SIDE WALL. MENS WATER CLOSET OT RIGHT OF URINAL REQUIRES MIN 15" SIDE WALL CLEARANCE. |
| 01/06/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 01/05/2005 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*1) PLBG FINAL IS OK FOR POOL BAR BLDG C LEVEL P-2 2) LOBBY WOMENS & MENS RESTROOMS BLDG D LEVEL 1 IS OK. 3) LOBBY BAR RESTROOMS WOMENS & MENS BLDG D LEVEL P-1 IS OK |
| 12/31/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* 1) WOMENS RESTROOM FOR POOL BAR IS OK 2) LOBBY BAR FINAL IS OK 3) NOTE: MENS POOL BAR RESTROOM THERE IS ONE WATER CLOSET THAT DOES NOT MEET MIN SIDE WALL CLEARANCE |
| 12/28/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/MENS & WOMENS RESTROOMS FOR BALLROOM RM'S #264, 268, 252, 256 |
| 12/15/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)STARBUCKS PLBG. FINAL IS OK 2)CLOSET FLANGES FOR BLDG G&H LEVELS 2, 3, & 4 ARE OK |
| 12/01/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG. FINAL IS OK FOR BLDG D LEVEL 5 2)OK FOR TEMP C/O FOR BLDG D & E GUEST ROOMS ONLY |
| 11/30/2004 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :*/1)HAD PRE CONSTRUCTION MEETING FOR CRITERIA ON SLEEVES AND VENTS FOR FIRE PITS |
| 11/29/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG FINAL IN BLDG D LEVEL 3 & 4 ARE OK 2)WATER DISTRIBUTION FOR PEDICURE BOWLS ARE OK BLDG G LEVEL 1 |
| 11/24/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG. FINAL IS OK FOR BLDG H BANQUET KITCHEN LEVEL P-1 AND IN BLDG G LEVEL P-1 EMPLOYEE CAFETERIA IS OK 2)OK FOR C/O |
| 11/23/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :* |
| 11/18/2004 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 11/17/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/PLBG. FINAL IS OK FOR BLDG E LEVEL 4 AND FOR BLDG G LEVEL P-1 MEN' & WOMENS LOCKER RMS ONLY 2)PLBG FINAL IS OK FOR BLDG D LEVEL P-1 BATHROOM B-205 & B-207 |
| 11/16/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG. FINAL IS OK FOR ENTIRE WING OF BLDG. E LEVEL 3 |
| 11/09/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG FINAL IS OK FOR BLDG E LEVEL P-1 AND LEVEL 2 |
| 11/05/2004 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection :*/1)PLBG FINAL IS OK FOR BLDG A, B & C LEVEL P-2 THRU LEVEL 5 2)PLBG FINAL IN CORRIDOR BLDG D, F, G, & H ONLY 3)PLBG FINAL IN CORRIDOR BLDG I & J NOT COMPLETE @ THIS TIME. 4)OK FOR TEMP C/O IN THESE AREAS ONLY |