Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T03BU02343

Parcel: 14027041A


Addresses:

6151 S TUCSON BL


Inspection Status: Approved

Inspection History: GRADING - FINAL

Permit Number - T03BU02343

Inspection Description - GRADING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
02/16/2007 GRADING - FINAL Approved Contractor address punch list.
11/30/2006 GRADING - FINAL Not Applicable Met Jim Femling on site went over grading issues.
11/21/2006 GRADING - FINAL Partial Approval Met on site with Nick site super, went over grouted rip rap placement and security barrier around basins.
11/16/2006 GRADING - FINAL Partial Approval Talked to Nick in regards to slope stabilization in basin. I explained to Nick that 2 to1 and steeper get grouted rip rap with a tow down at the bottom of the slope. NO GROUTED RIP RAP ON THE FLOOR OF THE BASIN.
09/19/2006 GRADING - FINAL Partial Approval Contractor continues to work on punch list. Contractor addressed items 2, 3, 9, 12 and 15.
08/29/2006 GRADING - FINAL Partial Approval Gave punch list to Nick site super and went over items.
08/15/2006 GRADING - FINAL Not ready for Inspection Completed punch list.
Solar Industries
T03BU02343
Punch List
8/15/06
1. Stabilize all areas disturbed by construction.
2. Install bollards in trash enclosure.
3. Install bollards around electric box.
4. Install handrail for all basins with 4 to 1 slopes or steeper and hold more then 2 feet of water.
5. Rip rap all 2 to 1 slopes in detention basins.
6. Address erosion in basin.
7. Have all changes to drawings approved at 210 N. Stone.
8. Backfill all open holes.
9. Install sidewalk to right-a-way. Per Development Standards.
10. Clean all silt out of detention basins.
11. Backfill sides of weir.
12. Install wheel stops eastside of building.
13. Provide letter from engineer to certifying drainage and detention basins. Per chapter XIV, section 14.2 (7).
14. Complete all bike parking.
15. Repair sinkhole and erosion northeast corner of parking lot.
16. Stabilize discharge side of weir. (was rip raped)
17. Have engineer address erosion under wall openings into basins.
06/14/2006 GRADING - FINAL Correction Required Spoke to Nick site super in regards to grading on west side of building. West side of building is not built per the approved plans. I told Nick he will need to submit a revised drawing with all site changes on it and have it approved by City of Tucson before a C of O could be issued.
03/02/2006 GRADING - FINAL Partial Approval Inspected trench for stormsewer pipe. Trench and rebar installed per apporved plans. Project engineer instructed contractor to get compaction test on pipe on north side of project that is buried. I told Nick I would need to copy of the Compaction test. Nick said he would make a copy for me at a later date.
09/28/2005 GRADING - FINAL Partial Approval Inspected footing for retaining wall (eastside of detention basin) westside of property.
Per contract drawing.