Inspection Status: Approved
Inspection History: GRADING - TIER REV
| Date |
Description |
Inspector |
Results |
Comments |
| 01/11/2010 |
GRADING - TIER REV |
|
Approved |
|
| 08/20/2009 |
GRADING - TIER REV |
|
Prior to Final Inspectn |
Need conditions of permit met for final approval. Including geotech post trench construction drain down confirmation (24). Left message with Sam at KB and discussed with Arden (EOR). |
| 08/07/2009 |
GRADING - TIER REV |
|
Approved |
Spoke with Wocky who was inquiring about what the next submittal req's were. I stated that we'd need: Final RevGP with as-built data for outlets and inlets for all basins & drainage improvements, showing new trenches, and other as-built data. 2 copies of plans, one copy of previously approved plan, closure letters (cover letter, substantial completion, drianage confoemnace letter with current perc test results for those basins that needed trenching / had drain down issues). |
| 05/11/2009 |
GRADING - TIER REV |
|
Approved |
Met w/ Arden Ranshaw regarding proposed revisions to some basins 11MAY09. Revisions approved 4JUN09. Asbuilts required for final approval. |