Inspection History Details
Permit: T03BU00974
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2010 | STORMWATER FOLLOW-UP INSP | Approved | Gravel bags removed from CB's, site stabilized. | |
| 11/25/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | Gravel bags need to be removed from CB's | |
| 07/11/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | BMP's NOT IN PLACE OR IN NEED OF REPAIR EROSION IN DRAINAGEWAY WHERE STANDING WATER IS EVIDENT (SEE PICTURES T02BU00133) MET WITH RON BARAIN (SP?) WITH KB HOMES 603-2655. SWPPP MAINT SERVICES WAS AT MEET AS WELL. RCVD FOLLOW-UP CALL FROM RICHARD (SWPPP MAINT SVCS 702-348-6957) TO ADVISE ALL BMP's IN PLACE AND READY FOR RE-INSPECT 7/12 |
|
| 03/13/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | STANDING WATER IN MULTI PURPOSE DRAINAGEWAY STANDING WATER WHERE DG WALKWAY HAS BEEN PLACED |
|
| 06/06/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Inspection was performed to note how many lots have unfinished sidewalks. SWPPP was highlighted with these areas and given to Dave Roberts for review. | |
| 05/06/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | THIS SITE IS IN FAIRLY GOOD CONDITION AND HAS NO STORM WATER CONCERNS AT THIS TIME. BUILDING IS PROGRESSING STEADILY. | |
| 01/04/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | STORM WATER FOLLOW-UP INSPECTION "V" DITCH ALONG THE N. PARIMETER HAS BEEN COMPLETED. MAINTAIN INSPECTIONS FOR THE NOTHERN SECTION OF THE W. PARIMETER FOR ANY POTENTIAL RUN-OFF. NO OTHER STORM WATER CONCERNS AT THIS TIME. |
|
| 12/28/2004 | STORMWATER FOLLOW-UP INSP | Partial Approval | CONTACT WAS MADE WITH GRANITE CONSTRUCTION SUPER ANDY WASH (237-0873). REQUEST WAS GIVEN TO PROVIDE ADDITIONAL STORM WATER CONTROL VIA "V" DITCH ALONG THE N AND NW PARIMETERS. ANDY EXPLAINED HE WOULD HAVE THIS DONE THIS WEEK. RE-INSPECTION IS SCHEDULED FOR TUESDAY THE 4TH. |