Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/01/2004 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* |
| 10/03/2003 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) COMPLETE TIE-IN TO EXISTING SEWER IN CENTER OF ALLEY WITH APPROVED TRANSITION FITTINGS 2) UNDERSLAB OK TO CLEANOUT EXTERIOR |
| 08/14/2003 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection 0000*1) INSTALL BANG PLATE NAIL PROTECTION ALL PLBG LINES. 2) PLAN CALLS FOSR COPPER (CHANGE PLAN TO PLASTIC) AS BUILT 3) H20 PIPE LEAKING INTO WATER HEATER. 4) THERE IS NO APPROVED TRANSITION FROM ABS. DRAIN PIPING TO WHITE CASITE SEWER LINE, MUST REPLACE OLD LINE FROM HOUSE TO SEWER CONNECTION IN ALLEY. 5) ABS PIPING REQUIRES 12" MIN COVER. 6)MUST COMPLETE ALL TRADES ( BLDG ELEC MECH GAS ) THEN RECALL FOR ALL INSPECTIONS. 7) MUST FIRE RATE CARPORT IF LESS THAN 3' TO P/L. 8) REMOVE ALL OLD PIPING (NOT TO BE REUSED) 9) UNCOVER AL H20 LINES OUTSIDE OF HOUSE FOR INSP. 10) STOPPED INSPECTION. |