Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T02CM04709

Parcel: 120052730

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Permit Number - T02CM04709

Inspection Description - PLUMBING - ROUGH, SOIL

Inspection Status - Approved

Date Description Inspector Results Comments
11/13/2002 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection 0000*
1.) ABS UNDERGROUND ACCEPTED BY ARCHETED WATER TEST ONE TEN FOOT RISER OK.
2.) TYPE "L" UNDER SLAB ACCEPTED BY ARCHETECT OK PRESSURE TEST OK
3.) OK TO BACKFILL.
11/12/2002 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection 0999*
1.) ALL SINKS REQUIRE CLEAN OUTS
2.) NEED LETTER FROM ARCHETECT ALLOWING MULTIPLE POINTS OF CONNECTION ALONG NORTH WALL.
3.) PLUMBER ADDED FLOOR SINK AND CLEAN OUT RETEST.
4.) DWV AND COPPER NOT INSTALLED PER PLAN.
11/06/2002 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*A.) ABS DWV UNDERGROUND OK W/TWO EXCEPTIONS A.) MOP SINK REQUIRES FULL SIZE CO. B.) DID THE PLUMBER MISS A FLOOR SINK ON THE EAST WALL?
2.) DONT FORGET ALL SINKS REQUIRE CLEAN OUTS.
3.) NEED LETTER FROM ARCHETECT ACKNOWLEDGING POINTS OF CONNECTION ALONG NORTH WALL.
2.) DID THE PLUMBER MISS A FLOOR SINK ON THE EAST WALL?
B.) DONT FORGET ALL SINKS REQUIRE CLEAN OUTS.
C.) NEED LETTER FROM ARCHETECT ACKNOWLEDGING POINTS OF CONNECTION ALONG NORTH WALL.