Inspection Status: Approved

Inspection History: PLUMBING - SEWER HCS CONNECT

Date Description Inspector Results Comments
10/24/2002 PLUMBING - SEWER HCS CONNECT Approved IVRS - Inspection 0000*
10/03/2002 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection 0000*
09/26/2002 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection 0000*1.) THE PLUMBING INSPECTOR HAS REQUESTED MORE THAN ONCE FOR YOU TO PROVIDE A LISTING FOR HEAVY DUTY CAST IRON USED ON THIS SEWER. PROVIDING A SECTION OF PIPE FOR THE INSPECTOR TO LOOK AT IS NOT THE SAME THING AS PROVIDING AN APPROVED LISTING. IN AN EFFORT TO EXPEDITE THIS PROJECT, AND BECAUSE THIS INSPECTOR RECOGNIZES THE PRODUCT USED, YOU HAVE PERMISSION TO COVER SEWER TO DIRECTIONAL CLEAN OUT ONLY. DONT FORGET TO INVOLVE PC WWM DURING BACKFILL IN THE STREET. 2.) PROVIDE APPROVED REVISED PLAN FOR 4" BRANCH TAKEN OFF IMMEDIATELY UPSTREAM OF CLEAN OUT. DO NOT COVER UP STREAM OF CLEAN OUT. EXPOSE ALL SEWER PIPING UP STREAM OF CLEAN OUT FOR INSPECTION. 3.) SHADE ALL APPROVED PIPING WITH AT LEAST 6" OF CLEAN FILL BEFORE USING NATIVE SOILS.
09/24/2002 PLUMBING - SEWER HCS CONNECT Denied IVRS - Inspection 0999*1.) SEE IAPMO INSTALLATION STANDARD IS 6-93 301.1.1.2. IDENTIFICATION SHALL BE READILY VISIBLE TO THE INSPECTOR. 2.) SEE NOTE #2 9/16/02 MUST HAVE LISTING ON JOBSITE FOR HEAVY DUTY CAST IRON OR DUCTILE PIPE. 3.) SEE IS 6-93 310.0 AND 310.0 AND 314.3 PIPING TO BE INSTALLED ON A FIRM BED IN PRACTICAL ALIGMENT, AND IN A WORKMANSHIP LIKE MANNER. 4.) REVIEW 7180 GRADE, SUPPORT AND PROTECTION OF BLDG SEWER EXPOSE ALL OF THE BLDG SEWER AND REMOVE ALL AGGREGATE AROUND PIPE. PIPE TO BE LAID ON A FIRM BED WITH APPROVED MATERIALS. BRING IN SUFFICIENT CLEAN FILL TO SHADE PIPE T0 6" ABOVE PIPE. 5.) SDR 35 CLEANOUT TO BE WYE BRANCH FITTING SEE 707.7 & 707.6 6.) ABS ROUGH SOIL UNDERGROUND OK WATER TEST OK OK TO COVER WITH CLEAN FILL.
09/16/2002 PLUMBING - SEWER HCS CONNECT Denied IVRS - Inspection 0999*1.) MUST HAVE CAST IRON ALL THE WAY TO HCS TAP. 2.) MUST HAVE LISTING ON JOB VERIFY HEAVY DUTY CAST IRON MATERIAL. 3.) MUST USE PROPER TRANSITION @ SDR-35 TO CAST IRON. 4.) RE TEST SYSTEM.
09/13/2002 PLUMBING - SEWER HCS CONNECT Denied UNABLE TO LOCATE SITE SEWER PLAN. PLEASE PROVIDE APPROVED PLAN FOR BLDG SEWER AND TIE-IN AT MAIN IN STREET. ALL RIGHT OF WAY AND STREET INSTALLATION TO BE IN ACCORDANCE WITH PIMA COUNTY WASTEWATER MANAGEMENT.