Permit: T01CM03651
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2003 | ENGINEERING - FINAL | Approved | ||
| 02/11/2003 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 IS COMPLETED AND APPROVED. PROVIDE THE FOLLOWING: 1. RAINWATER SIDEWALK SCUPPERS FOR (3) LOCATIONS ON WEST SIDE OF BUILDING WHERE RAINWATER DISCHARGE FLOW ACROSS PEDESTRIAN WALKWAYS. ( SEE ATTACHED DEVELOPMENT STANDARDS NO. 2-08.0) 2. DEFINE DRAINAGE SWALE AND RETENTION BASIN AS SHOWN ON UTILITY & GRADING PLAN. 3. DRAINAGE IMPROVEMENT AT NORTH SIDE SHALL CONFORM TO SPECIFICATIONS ON THE UTILILTY & GRADING PLAN. |
|
| 02/03/2003 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR PERMIT T01BU02177 IS COMPLETED AND APPROVED. |
|
| 01/17/2003 | ENGINEERING - FINAL | Denied | SITE IS NOT READY FOR INSPECTION UNTIL OPEN TRENCHES ARE BACKFILLED AND RAIN GUTTER DOWNSPOUTS ARE NOT DIRECTED TO SIDEWALKS. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR PERMIT T01BU02177 IS COMPLETED AND APPROVED. |