Permit: T01CM03651


Addresses:

5355 E 29TH ST

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
02/27/2003 ENGINEERING - FINAL Approved
02/11/2003 ENGINEERING - FINAL Partial Approval TEMPORARY C OF O APPROVED.
FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 IS COMPLETED AND APPROVED.
PROVIDE THE FOLLOWING:
1. RAINWATER SIDEWALK SCUPPERS FOR (3) LOCATIONS ON WEST SIDE OF BUILDING WHERE RAINWATER DISCHARGE FLOW ACROSS PEDESTRIAN WALKWAYS. ( SEE ATTACHED DEVELOPMENT STANDARDS NO. 2-08.0)
2. DEFINE DRAINAGE SWALE AND RETENTION BASIN AS SHOWN ON UTILITY & GRADING PLAN.
3. DRAINAGE IMPROVEMENT AT NORTH SIDE SHALL CONFORM TO SPECIFICATIONS ON THE UTILILTY & GRADING PLAN.
02/03/2003 ENGINEERING - FINAL Partial Approval TEMPORARY C OF O APPROVED.
FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR PERMIT T01BU02177 IS COMPLETED AND APPROVED.
01/17/2003 ENGINEERING - FINAL Denied SITE IS NOT READY FOR INSPECTION UNTIL OPEN TRENCHES ARE BACKFILLED AND RAIN GUTTER DOWNSPOUTS ARE NOT DIRECTED TO SIDEWALKS.
PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR PERMIT T01BU02177 IS COMPLETED AND APPROVED.