Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2001 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection 0000* PERMANENTLY AFFIX METAL TAG TO REGULATOR ON ROOF | |
| 03/30/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000* | |
| 03/02/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000* 1) BATHROOMS STUBBED UP THROUGH THE FLOOR 2) MOP SINK AND BREAKROOM SINK RISERS ONLY 3) DWV ABS UNDERGROUND OK WATER TEST OK 4) OK TO COVER 5) SHOWERS AND FLOOR DRAINS INSTALLED FOR T.I. TO BE APPROVED LATER-OK TO COVER 6) PARTIAL WATER RISER OK FOR BLDG 4 ABR SIL-FOS'D JOINT UNDER SLAB OK BLDG 5 NCS 100# TEST OK 7) BLDG SEWER 6" SDR-35 OK TO SIDEWALK 10' WATER TEST OK OK TO COVER WILL INSP. FINAL CONNECTION AT STREET CUT |