Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/28/2000 | ELECTRIC - UNDERGROUND | Approved | ||
| 12/18/2000 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection 0000* OK 4" TO SERVICE OK 4" TO TRANSFORMER |
|
| 12/13/2000 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection 0000* 4" PVC CDTs AROUND BACK OF BLDG ARE |
|
| 12/11/2000 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection 0000* POWER AND COMM PVC FROM POWER BANK TO 1ST RISER POINT BEFORE GEN PAD |
|
| 12/08/2000 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection 0000* TWO 4" SLABS AND 3-1" STUBS INTO POWER EQUIPMENT SLAB, OK THANKS, CALL FOR INSPECTION OF REMAINING U/G WHEN INSTALLED AND BEFORE BACK FILLING ANY TRENCHES |