Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case: S20-031

Parcel: 132191450

Inspection Status: Re-inspection required

Inspection History: TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance)

Plan Number - S20-031

Inspection Description - TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance)

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
08/11/2023 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) Re-inspection required Full and Final Release, Lots 1-6
09/18/2023 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) Re-inspection required Reach out to Jesus Villescaz for plans.
10/05/2023 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) Re-inspection required
11/13/2023 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) Passed cracks fixed inspection passes