Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP22-0267
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/05/2024 | ENGR Engineering Final | Not Ready | Trash enclosure #4 vertical and horizontal rebar is in footers and bollard placement is per COT specs and okay to pour concrete. | |
| 05/02/2024 | ENGR Engineering Final | Partial Pass | Poured the floor and the apron for the trash enclosure on the south west side of the project | |
| 06/12/2024 | ENGR Engineering Final | Partial Pass | Contractor needs to complete the basin on the south east corner of the project. Contractors waiting for TEP to run the electrical lines underneath the basin. | |
| 07/30/2025 | ENGR Engineering Final | Passed | ||
| 09/20/2024 | ENGR Engineering Final | Partial Pass | Superintendent has informed me that site is not yet completed | |
| 10/14/2024 | ENGR Engineering Final | Not Ready | Job is not yet completed as per the super on site, for the engineering final all items/buildings and construction need to be completed. | |
| 10/16/2024 | ENGR Engineering Final | Partial Pass | Okay for TCO level 4. possible revision pending. |