Permit: DP22-0265

Parcel: 10603054B


Addresses:

3250 N STONE AV

Inspection Status: Partial Pass

Inspection History: COT - ENGR - Stormwater

Date Description Inspector Results Comments
01/09/2024 COT - ENGR - Stormwater Partial Pass Utility work in progress. Track out noted.
01/17/2024 COT - ENGR - Stormwater Partial Pass material pile noted outside of fence
03/04/2024 COT - ENGR - Stormwater Passed
03/04/2024 COT - ENGR - Stormwater Passed
07/13/2023 COT - ENGR - Stormwater Partial Pass
07/28/2023 COT - ENGR - Stormwater Not Ready material and debris piles on site, no controls in place. Provide Stormwater controls as needed. Provide concrete containment.
09/19/2023 COT - ENGR - Stormwater Partial Pass No issues at this time
09/26/2023 COT - ENGR - Stormwater Partial Pass
11/14/2023 COT - ENGR - Stormwater Partial Pass Construction debris on site. No controls in place.
12/27/2023 COT - ENGR - Stormwater Partial Pass Project is nearing completion. Large piles of construction debris on site.