Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2026 |
ENGR - Drainage Structures |
|
Partial Pass |
Contract is good to pour the top of the arch culvert |
| 06/22/2026 |
ENGR - Drainage Structures |
|
Partial Pass |
contractor inform me that trash enclosure on the north east corner of the project will be grouted at 4 foot and then at 6 foot |
| 11/13/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Arch inspections should be called in on this item. |
| 12/08/2025 |
ENGR - Drainage Structures |
|
Not Ready |
Transfers installed with skew, reinstall perpendicular to centerline |
| 12/19/2025 |
ENGR - Drainage Structures |
|
Re-inspection required |
broken concrete is an unacceptable bar support. Excessive clearance to form and excessive/insufficient cover in multiple areas. All expansion joints are missing chamfer and are not trimmed correctly. Wing reinforcing needs to be trimmed and spliced as appropriate. |
| 12/23/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Begin installing outside forms. Approval from EOR required prior to pouring deck. |
| 12/30/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
contractors good to pour the floor the wings of the con arch |