Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2026 | ENGR Paving | Partial Pass | Concrete PAAL, section north of round-a-bout: subgrade and reinforcement are good. Okay to pour this section. | |
| 07/21/2026 | ENGR Paving | Partial Pass | Reinforced concrete cul-de-sac at main entrance: north section of is poured. West section base and reinforcement are good, okay to pour. East section base and reinforcement are good, okay to pour. South section base and reinforcement are good, okay to pour. | |
| 07/23/2026 | ENGR Paving | Partial Pass | Sub-grade for the east half of the north road: PAAL and parking stalls’ depth, slopes, and compaction are good. Okay to lay AB. | |
| 07/28/2026 | ENGR Paving | Partial Pass | Sub-grade at North entrance from Bear Canyon: Depths and compaction are good. Okay for AB. | |
| 07/29/2026 | ENGR Paving | Partial Pass | AB on East side and East half of Northside, some areas need adjustment on North drive. Revisit tomorrow morning prior to pave. | |
| 07/30/2026 | ENGR Paving | Partial Pass | East PAAL and parking is good to pave. Northern entrance driveway from Bear Canyon is good to pave pending Right-of-Way's inspection. North-East PAAL on the curve has been adjusted down, is good to pave pending tack coat. North PAAL between East refuse enclosure and middle intersection is good to pave pending tack coat application. |
|
| 11/13/2026 | ENGR Paving | Partial Pass | Pending pictures of a few areas that are too low and a few that need to be shaved that were marked-ABC okay to pave middle rd running south/north 3" AC. Snap chalk lines on curbs for 6” reveal and pave to them. | |
| 11/16/2026 | ENGR Paving | Partial Pass | North road from last bullnose at NW corner to the middle road that has just been paved to the East. Okay to pave this section.... Hubs are correct. PAAL is correct at 3". Parking bays will require extra asphalt from the PAAL to the curb reveal. Extra .5" at PAAL and then taper to +/- 0" at curb reveal. This is for all the bays in this section. Future sections will be graded correctly so parking bays do not taper but are a consistent 2.5" as designed per plan. Schedule inspections for paving so that inspection occurs the day before paving from now on. Not on same day. It will not be ready otherwise. |
|
| 11/17/2026 | ENGR Paving | Canceled | Contractor notified me to cancel | |
| 11/20/2026 | ENGR Paving | Not Ready | West Road AB inspection-Spillway depressed curb is broken, displaced and elevation is not to plan. AB per plan at spillway should slope 2% downgrade out the spillway- it does not. Across PAAL from spillway handicap parking slope is not correct and curb adjacent to it is over 3%. These issues need to be corrected in addition to other areas that need to be adjusted that I discussed with contractor. Reschedule when ready. |