Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 01/25/2024 |
ENGR Grading Final |
|
Not Ready |
No activity on site at this time. No change to Grading since last inspection. Building appears to be nearly complete. |
| 03/06/2024 |
ENGR Grading Final |
|
Partial Pass |
utility installations In progress. Grading activities have resumed. |
| 04/10/2024 |
ENGR Grading Final |
|
Passed |
|
| 04/12/2024 |
ENGR Grading Final |
|
Partial Pass |
complete everything is shown on the approved plans remove the rolloff dumpster from the site. This inspection will be rescheduled for Monday for the final if everything is completed as shown on the approved plans. What are the items that is missing currently is the striping from the ramp access of the parking space to the west to the handicap access ramp located at the north west corner of the building. This will need to be completed prior to the final approval of this permit and this site next week |
| 04/12/2024 |
ENGR Grading Final |
|
Passed |
See the comments on the other engineering grading for this site. This one is being approved at this time. |
| 08/03/2023 |
ENGR Grading Final |
|
Not Ready |
on site construction vertical for building, only. grade minimal. |
| 08/09/2023 |
ENGR Grading Final |
|
Partial Pass |
concrete placement for solid waste enclosure floor was in process when inspector arrived. single photo was provide showing reinforcement grid for floor. please send picture to 520-349-7643. |
| 08/09/2023 |
ENGR Grading Final |
|
Partial Pass |
concrete placement for solid waste enclosure was occurring at time of inspection. a singe picture was provided showing enclosure floor reinforcing, which appeared correct. please send picture and engineers letter stating enclosure is to code. |
| 08/09/2023 |
ENGR Grading Final |
|
Passed |
|
| 10/27/2023 |
ENGR Grading Final |
|
Not Ready |
no grading activity on site at this time. |
| 12/08/2023 |
ENGR Grading Final |
|
Not Ready |
No site activity at this time. Plans are under review. Building appears to be nearly complete. |