Inspection History Details
Inspection Status: Not Ready
Inspection History: SITE - Stormwater Setup and Controls
Permit Number - DP22-0098
Inspection Description - SITE - Stormwater Setup and Controls
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | SITE - Stormwater Setup and Controls | Not Ready | ||
| 01/25/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | The stormwater set up and control is good at this time. The contractor has pour pour concrete for stem walls and retaining walls without a city inspection. They’re in the progress of excavating for catch basin I informed the contractor to give us a call before pouring. I also informed the contractor that they need to call Lynn every two weeks for inspections | |
| 03/01/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Settings steel for six catch basins everything’s good at this time | |
| 10/19/2023 | SITE - Stormwater Setup and Controls | Passed | ||
| 12/06/2022 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Good to backfill the storm drain |