Inspection History Details
Inspection Status: Not Ready
Inspection History: SITE - Stormwater Setup and Controls
Permit Number - DP22-0003
Inspection Description - SITE - Stormwater Setup and Controls
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | SITE - Stormwater Setup and Controls | Not Ready | ||
03/06/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Contractor install 12 inch HDPE pipe handsome 8 inch pipe | |
03/09/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Contractor to Pac- the rebar for the catch basins they did not wet set the rebar. | |
03/13/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Contractor formed up The catch based three on the southside and one catch basin on the northside all of them our good to pour. | |
03/14/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | The contractor formed collars around existing storm drain and new storm drain a. Collar one on the north side one on the southside. | |
08/16/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Ni issues at this time. | |
09/20/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Wattle needs ‘to be removed from site prior to recall. | |
10/24/2023 | SITE - Stormwater Setup and Controls | Passed |