Inspection Status: Not Ready
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2026 | PDSD Engineering Division Pre-Construction SITE | Not Ready | Jesus Lozano in contacts -Contractor wants to pour sidewalks in parking lot with no vertical separation to vehicle use area. Plan calls for raised sidewalk. He will need to meet with Site Engineering either Joe Macauley or Stephan Blood to work out workable plan. Do not pour these sidewalks. -Contractor needs full DP to start work |
|
| 09/01/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | Not ready to pour middle sidewalk or sidewalk area in front of church entryway doors yet. Schedule sidewalk inspection for me to check all these form before pour. Sidewalks from Bantam up to the church adjacent to the walls on either side are at asphalt elevation. This is okay but the rest of plan will be followed. |