Inspection Status: Not Ready
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 07/22/2024 |
|
|
Not Ready |
Not ready due to rain preventing them from tieing rebar properly. |
| 07/23/2024 |
|
|
Passed |
On the west side about half way down the footing there was a small amount of dirt under the bottom rows of rebar, insure this is cleaned out prior to pouring. |
| 08/01/2024 |
|
|
Partial Pass |
Retaining wall mid inspection prior to grout, water proof and backfill, at 5 rows of 8. |
| 08/05/2024 |
|
|
Partial Pass |
Wall has been partially grouted so backfill can start. Rest of the wall will be called in at a later time and inspections will proceed on those two sections. |
| 08/09/2024 |
|
|
Not Ready |
Due to the rains, the contractor will have to clean the trenches up and have them ready by first part of next week and will recall this inspection in and have it redone |
| 08/14/2024 |
|
|
Partial Pass |
Ready to pour/grout |
| 08/30/2024 |
|
|
Passed |
|