Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP21-0312

Parcel: 13704155A


Addresses:

5301 S NOGALES HY

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
01/23/2024 ENGR Grading Final Partial Pass Viewed Scour protection wall backfill 42’ x 4’ deep located at NE corner of building (1 )
01/25/2024 ENGR Grading Final Passed
01/26/2024 ENGR Grading Final Passed
05/25/2023 ENGR Grading Final Complete (Recurring) Contractor set the steel for the HEADWALL’s on the southwest side of the project good rapport
07/06/2023 ENGR Grading Final Not Ready Grading for the parking spaces and the driveway area
07/10/2023 ENGR Grading Final Not Ready Contractors installing RCP’s on the north west partial of the project. The gap in between the RCP’s gonna be closer and remove all the debris around the RCP before backfilling the steel for the HEADWALL in the footings are good.
08/02/2023 ENGR Grading Final Partial Pass Contractors setting up the form for the entryways, and the radius is for the entryways. Contractor will call me when the forms are up and ready to be inspected.
08/08/2023 ENGR Grading Final Not Ready The contractor is not ready to pour the footers for the trash and closures on the northwest side, and on the southwest side
08/09/2023 ENGR Grading Final Partial Pass The trash enclosure on the northwest side is missing a number four upright on the ends and in the center missing for number four. The south trash enclosure was missing phone number forge in the center one number four on the left-hand side at the end. Contractor will take a photo when they install the rebar and send them to me.
08/16/2023 ENGR Grading Final Not Ready Vertical rebar and bond beam not installed or even on site, will be re-called when ready.
09/07/2023 ENGR Grading Final Partial Pass North and South end trash enclosure floor and aprons okay to pour.
09/08/2023 ENGR Grading Final Partial Pass 450 linear feet of footer and vertical and horizontal rebar along entire West front of site for 30” screen wall is ready to be poured.
09/27/2023 ENGR Grading Final Partial Pass Entire West front entry and parking lot area will begin asphalt on Friday the 29th of this week.
09/27/2023 ENGR Grading Final Partial Pass Entire West side entry and parking lot area will start asphalt on Friday the 29th of this week.
10/06/2023 ENGR Grading Final Partial Pass 250’ site wall #4 rebar bond beam in place.
10/10/2023 ENGR Grading Final Partial Pass 31 footers at a depth of 9’ for covered parking,cantilever columns are in place and leveled ready for pour, conformtech has completed and passed there inspection.
10/11/2023 ENGR Grading Final Partial Pass Walked site with Clayton 13 cantilever column footers located on East side parking lot at a depth of 9’ are okay to pour concrete and have been inspected by conformatech.
10/17/2023 ENGR Grading Final Not Ready
10/18/2023 ENGR Grading Final Partial Pass All grout knock outs observed for grout.
10/30/2023 ENGR Grading Final Complete (Recurring) Overall Site has improved.
Comments were made about re-implementing wattle along rear fence line and repairing fence.
Stucco contractor had washed out on dirt between building 1 and 2, cleanup started right away to repair.
11/02/2023 ENGR Grading Final Partial Pass Sidewalk for East section of site is formed and grade compacted and is to pour concrete on Saturday 11/4