Permit: DP21-0218

Parcel: 13316030C

Inspection Status: Not Ready

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
10/26/2022 SITE - Stormwater Setup and Controls Not Ready
01/11/2024 SITE - Stormwater Setup and Controls Partial Pass same comments as yesterday. need engineers certified letter addressing stormwater grate connection to below grade stormwater tanks.
05/30/2024 SITE - Stormwater Setup and Controls Passed
08/10/2023 SITE - Stormwater Setup and Controls Partial Pass inspection was for storm water retention tanks that were installed and about to be backfilled. informed project supervisor need additional inspections and to stop backfilling. project supervisor provided manufactures specs as well as engineer of record comments. engineer will need to provide letter stating installation ion was per approved plans.

no concerns at this time. super provided images of installation and that they were forwarded to d. roberts.
08/11/2023 SITE - Stormwater Setup and Controls Partial Pass