Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 03/19/2024 | ENGR Engineering Final | Not Ready | ||
| 04/10/2024 | ENGR Engineering Final | Canceled | site supervisor cancelled and rescheduled. | |
| 04/17/2024 | ENGR Engineering Final | Partial Pass | fencing still present, windows not complete, work still being performed. | |
| 04/18/2024 | ENGR Engineering Final | Partial Pass | good for TCO4. outstanding items: pedestrian access onnorth side of building, stormwater retention basin, NWC building, depth, plans call for 7 inches, need details for TEP transformer, NWC building, rip/rap and landscaping, sump pump draining to sidewalk north 0f main entrance, no 6 inch grade separation between sidewalk and concrete pavement south of main entrance, trees by ADA parking areas, add 1 foot of concrete on south side of bicycle rack, is access ramp required from sidewalk to solid waste enclosure, roof drain splash pads east side, of building. need to confirm landscaping depths east side building. |
|
| 05/06/2024 | ENGR Engineering Final | Partial Pass | Partial pass this time. The following items still will need to be addressed prior to the final approval. 1) 6 inch vertical separation has not been provided on the north side of the office adjacent to the unloading zone. Area is 0 to 4 inches. 2) The elevator drain has been constructed only 4 feet away from the main doorway into the Storage Facility and will deposit water directly onto the sidewalk area on the west side of the building just north of the main pedestrian access point. This water needs to be directed to another location since it violates the code of no water being deposited directly onto pedestrian, access areas or sidewalks. |
|
| 05/16/2024 | ENGR Engineering Final | Partial Pass | Contractor still needs to clean up the construction equipment and material on the south end of the building | |
| 05/30/2024 | ENGR Engineering Final | Passed | ||
| 09/21/2023 | ENGR Engineering Final | Not Ready |