Permit: DP21-0218

Parcel: 13316030C

Inspection Status: Not Ready

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
10/27/2022 ENGR Engineering Final Not Ready
03/19/2024 ENGR Engineering Final Not Ready
04/10/2024 ENGR Engineering Final Canceled site supervisor cancelled and rescheduled.
04/17/2024 ENGR Engineering Final Partial Pass fencing still present, windows not complete, work still being performed.
04/18/2024 ENGR Engineering Final Partial Pass good for TCO4.

outstanding items:

pedestrian access onnorth side of building,

stormwater retention basin, NWC building, depth, plans call for 7 inches,

need details for TEP transformer, NWC building, rip/rap and landscaping,

sump pump draining to sidewalk north 0f main entrance,

no 6 inch grade separation between sidewalk and concrete pavement south of main entrance,

trees by ADA parking areas,

add 1 foot of concrete on south side of bicycle rack,

is access ramp required from sidewalk to solid waste enclosure,

roof drain splash pads east side,
of building.

need to confirm landscaping depths east side building.
05/06/2024 ENGR Engineering Final Partial Pass Partial pass this time. The following items still will need to be addressed prior to the final approval.
1) 6 inch vertical separation has not been provided on the north side of the office adjacent to the unloading zone. Area is 0 to 4 inches.
2) The elevator drain has been constructed only 4 feet away from the main doorway into the Storage Facility and will deposit water directly onto the sidewalk area on the west side of the building just north of the main pedestrian access point. This water needs to be directed to another location since it violates the code of no water being deposited directly onto pedestrian, access areas or sidewalks.
05/16/2024 ENGR Engineering Final Partial Pass Contractor still needs to clean up the construction equipment and material on the south end of the building
05/30/2024 ENGR Engineering Final Passed
09/21/2023 ENGR Engineering Final Not Ready