Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP21-0147
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/28/2022 | ENGR Engineering Final | BBENEDOON | Approved | Entered by VVERA1 - Approved |
09/27/2022 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Complete all remaining work and corrections as previously noted. |
09/12/2022 | ENGR Engineering Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN / LANDSCAPE IS NOT COMPLETED NEED TO COMPLETE THE RIPRAP AND INSTALL THE PLANTS AND D.G. |
08/30/2022 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by NGARCIA3 - not ready. Joe with Caldwel Watza construction. 5204513574 |
09/28/2022 | ENGR Engineering Final | BBENEDOON | Approved | Entered by VVERA1 - Approved |
09/27/2022 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Complete all remaining work and corrections as previously noted. |
09/19/2022 | ENGR Engineering Final | MERNANDEZ | Partial Approval | Entered by VVERA1 - PARTIAL NEED TO COMPLETE LANDSCAPE. |
09/13/2022 | ENGR Engineering Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Engineering has no issues it would prevent a temporary certificate of occupancy. |
09/12/2022 | ENGR Engineering Final | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - PARTIAL |
08/30/2022 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by NGARCIA3 - not ready. Joe with Caldwel Watza construction. 5204513574 |