Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 10/07/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Large material and debris piles on site. Provide concrete containment as required. |
| 09/16/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - continued |
| 07/28/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. No issues since last rain event |
| 07/14/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Ongoing construction no issues or concerns at this time. |
| 06/22/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - continued. no issues at this time. Material piles appear to be for the other two residential projects in this cul-de-sac. |
| 06/01/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - Continued. Trash and material storage within right of way additionally other construction sites have materials piled in cul-de-sac |
| 05/26/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - Continued |
| 05/17/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Trash and material containers in right of way. Building construction in progress. No site work at this time |
| 04/20/2022 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - Continued |
| 04/07/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN NO CONCERNS.
|
| 12/15/2021 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. No issues after last rain event |
| 11/10/2021 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - Continued. All dirt and debris contained on site. |
| 09/28/2021 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - 09154. Continued
|
| 09/24/2021 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by VVERA1 - 09154. Continued. No issues or concerns at this time.
|