Inspection History Details
Inspection Status: Complete (Recurring)
Inspection History: ENGR Grading Final
Permit Number - DP20-0272
Inspection Description - ENGR Grading Final
Inspection Status - Complete (Recurring)
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/02/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Contacts belongs to retail. Temporary fencing still in place. Building construction |
10/27/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by VVERA1 - Approved |
10/26/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Par app. Accessible walkways Walked the site with Mike from Epstein. |
10/21/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Courtesy inspection for Mike. Concrete ramp being poured at 9:15 AM. Reschedule inspection after work has been completed. |
10/20/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VVERA1 - Partially approved. Preparation for asphalt Repair. |
10/14/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved, drive through curbs and islands. |
10/05/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Accessibility modifications as needed at front entry. |
10/01/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - . Continue. Contractor installing accessible route at entrance. Mike with Epstein. |
09/30/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - 09185. Continued. Work on drive-through |
09/28/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - 09185. Continued. Contractor installing curbs. |
09/24/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continue. Drive-through grading in progress. Consult designing engineer for elevation discrepancies at accessible ramp. Mike the Epstein |
09/21/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Drive-through curbs |
09/14/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. Construction convex, Dumpster, portable toilet and temporary fencing in place. Material piles on site. No activity at this time |
08/26/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. Demo of work area. |
11/04/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by NGARCIA3 - Approved |
11/10/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - . Approved |
12/09/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - Approved. |
11/17/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - . Continued. Temporary fencing in place. Construction trailer is for TI. Shell work appears to be mostly complete. Mike with Epstein |
10/13/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Curbs and ramps have been installed. No activity on site at this time temporary fencing locked. |