Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP20-0201
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/31/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED |
07/08/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by RSALDAT1 - CN NEED TO GRAD THE PARKING LOT. |
07/02/2021 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by VLEON1 - PARTIAL, SITE GRADING WORK ALONG WITH VERTICAL WORK ON THE STRUCTURES HAPPENING AT THIS TIME |
05/11/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - |
03/30/2021 | ENGR Grading Final | DROBERTS | Continued | Entered by RSALDAT1 - CONTINUED AT THIS TIME, MET WITH ZACK FROM CANYON AND LOOKED AT THE TRASH ENCLOSURE THAT THEY HAVE CONSTRUCTED. THIS STRUCTURE WAS DONE BY AN EARLIER VERSION AND IS OVER 26 FEET IN LENGTH, NOT 28 PLUS FEET PER OUR CURRENT STANDARD DETAIL. I HAVE ADVISED THEM THAT SINCE IT WAS DONE BY A PREVIOUS DETAIL THAT WE WILL ACCEPT IT AS LONG AS THEY CANE MAINTAIN THE REQUIRED 10 FEET OF CLEAR SPACE IN BOTH SIDES OF THE STRUCTURE. HE WILL CALL ME FRO AN INSPECTION WHEN THE START TO SET THE BOLLARDS. |
02/22/2021 | ENGR Grading Final | DROBERTS | Continued | Entered by VLEON1 - CONTINUED, CREWS HAVE BEEN WORKING ON THE INSTALLATION OF 18 and 24 |
08/31/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED |
07/08/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by RSALDAT1 - CN |
07/02/2021 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by VLEON1 - |
06/10/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - GRADING THE PARKING LOT |
05/11/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE REBAR FOR TRASH BIN IS GOOD |
03/25/2021 | ENGR Grading Final | MHERNANDEZ | Partial Approval | Entered by VLEON1 - PARTIAL ON THE TRASH BIN GOOD TO GROUT |
03/25/2021 | ENGR Grading Final | MHERNANDEZ | Partial Approval | Entered by VLEON1 - PARTIAL ON THE TRASH BIN GOOD TO GROUT |
03/01/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE REBAR FOOTER FOR TRASH BIN NEED TO ADD NUMBER 4 BAR AT THE ENDS AND CORNERS |
03/01/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE REBAR FOOTING FOR TRASH BIN |
10/22/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
10/22/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |