Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 02/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 12/13/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /REBAR INSPECTION FOR TRASH BIN FLOOR GOOD . |
| 12/10/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by RSALDAT1 - CONTINUED, OK TO POUR THE FLOOR SLAB AND APPROACH FOR THE TRASH ENCLOSURE LOCATED AT THE SOUTH WEST CORNER OF THE SITE PENDING ADDING ADDITIONAL SPACERS UNDER NEATH THE REBAR MAT. PROVIDE PHOTO OF THE ADDITIONAL SPACERS PRIOR TO THE PLACEMENT OF THE CONCRETE.
|
| 11/15/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /REBAR FOR THE WALLS .TRASH BIN. |
| 11/10/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN/ TRASH BIN FOOTER. |
| 11/09/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /POURED THE FRONT OF THE BUILDING DRIVEWAY 4” WAS NOT INSPECTED .NEED THE ENGINEER TO SIGN OFF ON IT |
| 04/06/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 03/29/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - PARTIAL AT THIS TIME, LANDSCAPING, ROCK RIP RAP, AND DECOMPOSED GRANITE IS BEING PLACED AT THIS TIME. THIS SITE WILL BE RESCHEDULED FOR FRIDAY OF THIS WEEK TO SEE HOW MUCH WORK IS NEEDED TO COMPLETE THIS SITE.
|
| 03/16/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - INTERMEDIATE CREWS LOOKING FOR ALL REMAINING ITEMS PUNCHLIST CN /. NEED TO FINISH THE LANDSCAPE AND THE IRRIGATION SYSTEM.WHICH INCLUDES THE RIP RAP IN THE BASIN.AND PLANTING THE SHRIBS.
|
| 02/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 12/03/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by RSALDAT1 - CONTINUED, THE CREWS ARE WOKING ON FINISH GRADING ALL THE EXTERIOR AREAS ON THE EAST SIDE OF THE PROJECT AND IN THE RIGHT OF WAY ALONG TUCSON BLVD. ON THE WEST SIDE OF THE PROJECT CREWS ARE WORKING ON POURING THE WHITE PAVEMENT WEST OF THE BUILDING AND GRADING AREAS FOR FUTURE PAVEMENT AND LANDSCAPING. |
| 10/28/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /POURED SOME CURB ON THE SOUTH END OF BUILDING. |
| 09/30/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VVERA1 - INTERMEDIATE IS CONTINUED, CREWS WORKING MAINLY ON THE STRUCTURE. I MET WITH THE GENERAL CONTRACTOR AND HIS SUBCONTRACTOR ABOUT THE TRASH ENCLOSURE THAT THEY WILL START WORKING ON THIS WEEK. I HAVE REMINDED THEM TO UTILIZE THE DETAILS THAT WE HAVE PROVIDED FO THEM AND TO SCHEDULE AN INSPECTION ONCE THEY HAVE THE REBAR PLACED READY TO POUR. |
| 06/15/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VLEON1 - |
| 03/22/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VLEON1 - |
| 03/12/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by RSALDAT1 - CONTINUED AT THIS TIME, CREWS CONTINUE TO WORK ON THE SUB-GRADE FOR THE SITE. |
| 03/11/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VLEON1 - |
| 03/10/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VLEON1 - |