Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - NPPO
| Date |
Description |
Inspector |
Results |
Comments |
| 08/16/2021 |
PDSD Site/Engineering Division - NPPO |
DROBERTS |
Approved |
Entered by RSALDAT1 - APPROVED |
| 07/19/2021 |
PDSD Site/Engineering Division - NPPO |
MHERNANDEZ |
Continued |
Entered by VLEON1 - CONTRACTOR CALL IN AND WOULD LIKE TO RESCHEDULE AT A LATER DAY |
| 07/16/2021 |
PDSD Site/Engineering Division - NPPO |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - 09190, 09031, 09160. Not ready. Work in progress. Parking spaces are 16 feet in length, plan specifies 18 feet. Depress all landscape areas as shown on plan ensure basins are installed to elevation specified. Complete all work and remove debris from site. |