| 07/16/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - All 14 inspections, approved. Please change status to final. |
| 03/25/2021 |
PDSD Engineering Division Pre-Construction SITE |
MHERNANDEZ |
Denied |
Entered by RSALDAT1 - 1809 N 13TH AVE:
THIS WAS NOT A PER-CONSTRUCTION.IT A 9027 ENGINEERING FINAL .NEED A LETTER FROM THE ENGINEER OF RECORD FOR THE TRUNCATED DOMES AND THE TRASH BIN AND THE STREET ACCESS .THE TREES NEED the 11/2 staking.downspouts need to be installed. |
| 03/25/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by VLEON1 - Partially approved FOR 443 W PLATA ST. Assist Martin with pre-construction meeting of project completed without inspections.
|
| 03/24/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Denied |
Entered by RSALDAT1 - Denied. Project nearing completion. No inspection history.
Contractor has been asked to schedule inspections from his development package permit. Jim at 603-6335.
|