Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP20-0052
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/11/2021 | ENGR Grading Final | MHERNANDEZ | Approved | Entered by VLEON1 - APPROVED |
02/04/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE |
02/11/2021 | ENGR Grading Final | MHERNANDEZ | Approved | Entered by VLEON1 - APPROVED |
02/04/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE |
11/12/2020 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by PAHUMAD1 - INSPECTION 09185 GRADING INTERMEDIATE IS PARTIAL AT THIS TIME, OK FOR TCO FOR THE FUTURE OPENING. LLOYD CONSTRUCTION MET ME ON SITE TO LOOK AT THE PROPOSED PATHWAY THAT THEY WILL BE USING IN THE FUTURE OPENING OF THE PAY BOOTHS. THERE IS WORK THAT IS STILL NEEDED IN THESE AREAS BUT IT WILL BE DONE UTILIZING TEMPORARY CLOSURES OF THE AFFECTED PAY BOOTHS AS NEEDED. |
11/10/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by PAHUMAD1 - Continue. Peter with Lloyd is now the superintendent for this project. Temporary fence has been relocated to accommodate opening the new entry |
11/02/2020 | ENGR Grading Final | DROBERTS | Continued | Entered by PAHUMAD1 - CONTINUED AT THIS TIME. MET WITH PETER AND AMY FROM LLOYD CONSTRUCTION TO LOOK AT THE WORK THAT HAS BEEN COMPLETED FOR THE TCO THAT THEY WILL BE SEEKING ON NOVEMBER 12TH. THEY WILL RESCHEDULE THIS INSPECTION FOR THAT DATE KNOWING THAT THE WORK AROUND THE ENTRY WILL BE COMPLETE AT THAT TIME. I HAVE REMINDED THEM THAT ANY REMAINING WORK WILL NEED TO BE FENCED OFF FROM THE PUBLIC, AND WORK COMPLETED DURING NON OPERATIONAL HOURS, OR FENCED OFF DURING WORK HOURS. |
08/05/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. 60 feet of stormwater piping between catch basins. Anthony with Lloyd |
07/31/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Stormwater piping and three catch basins. |
07/16/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Stormwater piping. Anthony with Loydd. |
06/17/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Ductile iron stormwater piping. Native Fill is acceptable for this material. Anthony with LLoyd construction 471-9612 |
05/22/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued.Contractors Performing demo |
02/18/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - Continue. Work in progress. Peter with LLoyd construction |
02/18/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Work in progress. Temporary fencing installed. Stormwater controls in place. |
02/25/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |