Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 12/03/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Approved |
Entered by PAHUMAD1 - |
| 10/27/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by PAHUMAD1 - Continued. Concrete containment in place. |
| 10/02/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. Discharge from site into catch basin in private parking area to the west
Large pile of material next to modified existing catch basin in drive-through
|
| 10/02/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. All issues have been corrected.
|
| 09/23/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. No issues at this time. |
| 07/22/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. No issues. Site opens into private parking lot. |
| 07/14/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. Controls in place |
| 07/09/2020 |
SITE - Stormwater Follow-up
|
BBENEDON |
Continued |
Entered by RSALDAT1 - Continue. Controls have been installed at catch basin. No issues at this time. By concrete containment water protections As needed