Permit: DP19-0257

Parcel: 11623108A


Addresses:

910 W STARR PASS BL

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
07/06/2022 ENGR Grading Final MHERNANDEZ Approved Entered by VVERA1 - APPROVED
02/07/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN / GRADING FOR D.G IN FRONT AND BACK OF THE APARTMENT BUILDING.
01/14/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - ) IS PARTIAL, CHECKED THE FORMS FOR CURBS WITHIN THE PROPERTY LIMITS. THE FORMS WITHIN THE RIGHT OF WAY WILL NEED TO BE INSPECTED BY THE TRANSPORTATION DEPARTMENT.
12/22/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN GOOD
12/15/2021 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN / FORMING FOR CURB AND SIDEWALK.FRONT PARKING LOT.GOOD
12/10/2021 ENGR Grading Final DROBERTS Continued Entered by VVERA1 - IS CONTINUED, THE CONTRACTOR HAS FORMED THE CURB AND SIDEWALK IN THE SOUTH SIDE PARKING LOT. I HAVE REMINDED THE CONTRACTOR THAT THEY WILL NEED TO REMOVED ALL LOOSE DIRT AND MUD FROM THE AREA TO ENSURE IT IS DRY BEFORE THEY PLACE THE CONCRETE NEXT WEEK.
10/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN
10/06/2021 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /FORMING FOR SIDEWALK
10/04/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN/ FORMING FOR SIDEWALK.
07/06/2022 ENGR Grading Final MHERNANDEZ Approved Entered by VVERA1 - APPROVED
05/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN FOOTER FOR THE WALL IN FRONT OF THE APARTMENTS.
12/22/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN /PLACING REBAR FOR TRASH BIN FLOOR.GOOD.
12/10/2021 ENGR Grading Final DROBERTS Not ready for Inspection Entered by VVERA1 - IS NOT READY AT THIS TIME, THE TRASH ENCLOSURE AND APPROACH WILL BE EXCAVATED NEXT WEEK AND THIS RE-INSPECTION WILL BE RESCHEDULED AT THAT TIME.
11/12/2021 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - PARTIALLY APPROVED, OK FOR THE PLACEMENT OF GROUT
10/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /FOOTER FOR TRASH BIN
07/12/2022 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/12/2022 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
06/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE CHECK FOR ACTIVITY
05/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -