Permit: DP19-0221

Parcel: 10503032C


Addresses:

5001 N ORACLE RD

Inspection Status: Passed

Inspection History: PDSD Engineering Division Pre-Construction SITE

Date Description Inspector Results Comments
09/15/2022 PDSD Engineering Division Pre-Construction SITE BBENEDON Approved Entered by VVERA1 - Approved
06/03/2022 PDSD Engineering Division Pre-Construction SITE BBENEDON Continued Entered by NGARCIA3 - Continued. Conversation with Chris from blue lion Destruction. Please schedule Grading inspections. 5001 N Oracle Rd,
02/01/2022 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by VVERA1 - Partially approved. Unscheduled courtesy preconstruction meeting with Tyler from clear contracting and Kris with blue lion builders at 400 6949 . Post SWPPP,NOI at front gate and schedule Stormwater inspection from your development package permit. Schedule grading rebar and intermediate inspections for trash enclosure and site work. Trash enclosure requires rebar at 32 inches on center.
01/27/2022 PDSD Engineering Division Pre-Construction SITE BBENEDON Not ready for Inspection Entered by VVERA1 - Not ready. Unscheduled inspection. Requesting that Tyler with clear contracting at246-7491 provide a copy of and post NOI
12/09/2021 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Unscheduled courtesy preconstruction meeting with Kris the general contractor and Tyler and Grading contractor. Contractor will start scheduling five from the development package permit.
09/07/2021 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Unscheduled courtesy preconstruction meeting. Cody with Wyco, 8018227322. New site superintendent. Tyler w/ clear contracting 520 246 7491 grading contractor. Please schedule a preconstruction meeting. Please provide SWPPP as required. Provide stormwater protections as needed. Ensure that no offsite discharge enters public drainage channel along the west end of the site. Note, minor erosion apparent in a few places at existing bank section. Schedule Grading inspections for all Stormwater piping, catch basins and trashing closure. Schedule biweekly Stormwater follow up inspections.
09/07/2021 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Unscheduled courtesy preconstruction meeting. Cody with Wyco, 8018227322. New site superintendent. Tyler w/ clear contracting 520 246 7491 grading contractor. Please schedule a preconstruction meeting. Please provide SWPPP as required. Provide stormwater protections as needed. Ensure that no offsite discharge enters public drainage channel along the west end of the site. Note, minor erosion apparent in a few places at existing bank section. Schedule Grading inspections for all Stormwater piping, catch basins and trashing closure. Schedule biweekly Stormwater follow up inspections.
09/07/2021 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. 5055 N ORACLE RD Unscheduled courtesy preconstruction meeting. Cody with Wyco, 8018227322. New site superintendent. Tyler w/ clear contracting 520 246 7491 grading contractor. Please schedule a preconstruction meeting. Please provide SWPPP as required. Provide stormwater protections as needed. Ensure that no offsite discharge enters public drainage channel along the west end of the site. Note, minor erosion apparent in a few places at existing bank section. Schedule Grading inspections for all Stormwater piping, catch basins and trashing closure. Schedule biweekly Stormwater follow up inspections.
09/07/2021 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. 5061 N ORACLE RD Unscheduled courtesy preconstruction meeting. Cody with Wyco, 8018227322. New site superintendent. Tyler w/ clear contracting 520 246 7491 grading contractor. Please schedule a preconstruction meeting. Please provide SWPPP as required. Provide stormwater protections as needed. Ensure that no offsite discharge enters public drainage channel along the west end of the site. Note, minor erosion apparent in a few places at existing bank section. Schedule Grading inspections for all Stormwater piping, catch basins and trashing closure. Schedule biweekly Stormwater follow up inspections.