Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2022 | SITE - Stormwater Follow-up | Complete (Recurring) | {Activity date: 10/19/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - continued. No issues on Oracle or river roads. Contractor has started to Remove large debris piles 5061 N ORACLE RD } ; {Activity date: 10/19/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5055 N ORACLE RD} ; {Activity date: 10/19/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 10/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Material and debris piles remain on site. 5001 N ORACLE RD} ; {Activity date: 10/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5075 N ORACLE RD} ; {Activity date: 10/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5061 N ORACLE RD} ; {Activity date: 10/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5055 N ORACLE RD} ; {Activity date: 09/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. The only issues or concerns at this time are with the large debris piles in the southwestern corner of the site as well as the section of handrail that needs to be repaired at basin seven connection to Pima wash. Additionally, Basin seven has standing water two days since last rain event} ; {Activity date: 09/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued} ; {Activity date: 09/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - . Continued. Note, there is standing water in basin number 7, two days after last rain event} ; {Activity date: 09/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 09/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue. Large material and debris piles remain in close proximity to Pima wash.} ; {Activity date: 09/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue. Large material and debris piles remain in close proximity to Pima wash.} ; {Activity date: 09/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continue. Large material and debris piles remain in close proximity to Pima wash. 5055 N ORACLE RD} ; {Activity date: 09/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Work continuing in the southwest portion of the site. Large material and debris piles remain. 5001 N ORACLE RD} ; {Activity date: 09/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5061 N ORACLE RD} ; {Activity date: 09/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5055 N ORACLE RD} ; {Activity date: 09/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time. All materials contained within site 5075 N ORACLE RD } ; {Activity date: 08/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5055 N ORACLE RD} ; {Activity date: 08/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5001 N ORACLE RD} ; {Activity date: 08/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued 5061 N ORACLE RD} ; {Activity date: 08/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continue} ; {Activity date: 08/05/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 08/05/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Stormwater protection and large dirt and debris piles remain contained on site at Southwest corner. 5001 N ORACLE RD} ; {Activity date: 08/05/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Stormwater protection and large dirt and debris piles remain contained on site at Southwest corner. 5061 N ORACLE RD} ; {Activity date: 08/05/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Stormwater protection and large dirt and debris piles remain contained on site at Southwest corner. 5055 N ORACLE RD} ; {Activity date: 07/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue. No issues} ; {Activity date: 07/13/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 07/13/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - . Continued. No issues at this time. Large Material and debris piles remain on site.} ; {Activity date: 07/13/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 07/13/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. large material and debris piles at southern portion of site and in parking area of existing abandon building to the north. } ; {Activity date: 07/06/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - Continued. Material and debris piles remain on site. No issues since last rain event} ; {Activity date: 06/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - continued} ; {Activity date: 06/17/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Additional controls installed at Southern portion of site. 5075 N ORACLE RD} ; {Activity date: 06/17/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Additional controls installed at Southern portion of site. 5061 N ORACLE RD} ; {Activity date: 06/17/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Chris with blue lion construction, asked to move and or ensure adequate containment of material piles in close proximity to The Pima wash. 5055 N ORACLE RD} ; {Activity date: 06/17/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Chris with blue lion construction, asked to move and or ensure adequate containment of material piles in close proximity to The Pima wash. 5001 N ORACLE RD} ; {Activity date: 06/15/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 05/18/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No issues or concerns } ; {Activity date: 05/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No evidence of contamination to Pima wash at this time. Large material piles and unfinished work remain along west and southern portions of the job site} ; {Activity date: 03/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Large material stock piles on site. Superintendent maintaining west side perimeter Stormwater controls.} ; {Activity date: 02/04/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time. Walked site perimeter adjacent to public wash with job superintendent Chris. All controls remain in place. 5055 N ORACLE RD} ; {Activity date: 01/21/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Contractor moving large debris piles and continued utility work in progress 5001 N Oracle Rd,} ; {Activity date: 01/12/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Concerned about large material piles at the north end of the site} ; {Activity date: 01/07/2022; Status: Continued; Inspector: BBENED |
|
| 10/26/2022 | SITE - Stormwater Follow-up | Re-inspection required | ||
| 11/17/2022 | SITE - Stormwater Follow-up | Deferred | Stormwater follow up inspection. Continued. Large debris pile remains at south western portion of site in proximity to Pima wash. |