Permit: DP19-0175

Parcel: 12419040J


Addresses:

555 S CHERRY AV

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
01/13/2022 ENGR Grading Final MHERNANDEZ Approved Entered by VVERA1 - APPROVED
08/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN/ NO ACTIVITY
08/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN /GRADING FOR CURB
08/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN /GRADING FOR CURB
05/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 555 S CHERRY AV
09/09/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Miramonti homes it’s constructing new buildings
08/11/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Utility work and rough grading has been completed. Building construction is underway
08/06/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. On- going utility work. Building construction has started.
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME, CONTRACTOR IS WORKING ON SITE GRADING, UTILITY INSTALLATION, FORMING FOR FUTURE CONCRETE WORK.
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME, CONTRACTOR IS WORKING ON SITE GRADING, UTILITY INSTALLATION, FORMING FOR FUTURE CONCRETE WORK.
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME, CONTRACTOR IS WORKING ON SITE GRADING, UTILITY INSTALLATION, FORMING FOR FUTURE CONCRETE WORK.
06/25/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Backfill of storm drains and domestic sewer. Installing domestic water mains.
06/22/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Contractor working on basin. Filter fabric installed.
06/12/2020 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - SITE VISIT AT THIS TIME, PHOTOGRAPHS OF SITE HAVE BEEN SENT TO BRIAN BENEDON, NO CONCERNS AT THIS TIME.
06/10/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - continued stormwater piping as shown
06/08/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved
06/08/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Stormwater piping. Pictures provided by Desert earth.
06/05/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Excavation and installation of storm drain piping. Bryan with Desert Earth. Inspection code is 9185, not 9170. Thanks
06/05/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Excavation and installation of storm drain piping. Bryan with Desert Earth.
06/03/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Backfill of underground basin. Bryan with Desert earth
05/29/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Storm tech chamber system below ground stormwater basin as shown between building 11 and building one.
05/12/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Preparing for stormwater piping and underground basin installation. Installing main water lines.
05/05/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Contractor installing sewer utility and Preparing for storm water pipe Installation
04/20/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Contractor installing say utilities.
03/19/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Contractor is over excavating and storing materials on site.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Grubbing has been completed and site grading is in progress. A long pile of dirt has been placed near west property line.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Grubbing has been completed and site grading is in progress. A long pile of dirt has been placed near west property line.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Grubbing has been completed and site grading is in progress. A long pile of dirt has been placed near west property line.
01/18/2022 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
01/18/2022 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
01/18/2022 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME.
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME.
07/27/2020 ENGR Grading Final DROBERTS Continued Entered by JSCHNEI2 - CONTINUED AT THIS TIME
06/25/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Backfill of storm drains and domestic sewer. Installing domestic water mains.
06/25/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Backfill of storm drains and domestic sewer. Installing domestic water mains.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Contractor on site.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Contractor on site.
03/12/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Contractor on site.