Permit: DP19-0142

Parcel: 10707019A


Addresses:

1066 W GRANT RD


Inspection Status: Passed

Inspection History: PDSD Site/Engineering Division - Landscaping

Permit Number - DP19-0142

Inspection Description - PDSD Site/Engineering Division - Landscaping

Inspection Status - Passed

Date Description Inspector Results Comments
02/07/2020 PDSD Site/Engineering Division - Landscaping BBENEDON Approved Entered by DMERANZ1 -
02/06/2020 PDSD Site/Engineering Division - Landscaping IVR USER Cancelled Entered by IVR USER - IVRS - AP canceled
02/03/2020 PDSD Site/Engineering Division - Landscaping DROBERTS Partial Approval Entered by DROBERT5 - THIS SITE IS OKAY FIOR A TCO AT THIS TIME PENDING ALL OTHER INSPECTIONS. THIS SITE IS NOT READY AT THIS TIME FOR A FINAL, ALL THE LANDSCAPE ITEMS HAVE NOT BEEN COMPLETED AT THS TIME. COMPLEETE PLANTING THROUGHOUT AS SHOWN ON THE APPROVED PLANS. PLACE DG OR HYDROSEED IN ALL THE REMAINING DISTURBED AREAS THAT REMAIN WITH DISTURBED SOIL. THIS WILL INCLUDME THE AREA NORTH OF THE NEW TRASH ENCLOSURE, AND ALL AREAS TOWARDS THE NORTHWEST CORNER OF THE SITE. INSTALL THE HANDICAP SIGNS AT THE PROPER HEIGHT OF 7 FOOT CLEARANCE ABOVE GRADE. REMOVE THE BOLLARDS AS DISCUSSED ON THE SOUTH SIDE OF THE SITE ADJACENT TO THE FUTURE SIGN LOCATION, SO THAT THE CORRECT NUMBER OF PARKING LOCATIONS CAN BE ACCOUNTED FOR.
01/31/2020 PDSD Site/Engineering Division - Landscaping BBENEDON Approved Entered by DMERANZ1 - Work in progress will inspect and final. 6 inch depression shown for all water harvesting areas. Walk the site with the GC
02/13/2020 PDSD Site/Engineering Division - Landscaping RLEDONNNE Approved Entered by DMERANZ1 -
02/03/2020 PDSD Site/Engineering Division - Landscaping DROBERTS Not ready for Inspection Entered by DROBERT5 - THIS SITE IS NOT READY AT THIS TIME, ALL THE LANDSCAPE ITEMS HAVE NOT BEEN COMPLETED AT THS TIME.COMPLEETE PLANTING THROUGHOUT AS SHOWN ON THE APPROVED PLANS. PLACE DG OR HYDROSEED IN ALL THE REMAINING DISTURBED AREAS THAT REMAIN WITH DISTURBED SOIL. THIS WILL INCLUDME THE AREA NORTH OF THE NEW TRASH ENCLOSURE, AND ALL AREAS TOWARDS THE NORTHWEST CORNER OF THE SITE.