Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/08/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by VLEON1 - |
| 04/08/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by VLEON1 - |
| 03/12/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued. Parking canopies installation in progress.
|
| 01/26/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VLEON1 - PARTIAL APPROVAL FINAL GRADING READY FOR ASPHALT AND FINAL GROUND COVERING |
| 01/26/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VLEON1 - PARTIAL APPROVAL FINAL GRADING READY FOR ASPHALT AND FINAL GROUND COVERING |
| 01/22/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VLEON1 - PARTIAL ROUGH GRADING IN PROGRESS |
| 01/07/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VLEON1 - Partially approved. Final grading for parking area. |
| 12/24/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Parking and landscaped areas grading and curbs |
| 12/15/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Rough grading and curb installations |
| 10/30/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Demolition for phase 2 started. |
| 10/23/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Perimeter fencing installed for phase 2. Demo has not started |
| 10/06/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by PAHUMAD1 - NO ACTIVITY AT FRONT BUILDING. MATERIAL STOCK PILES SO PRESENT ON WEST SIDE. |
| 08/05/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Landscaping in progress at new building. Dirt work. At north west corner of site. Perimeter temporary fencing Sterling Place south and west portions of site at new building.
|
| 06/29/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Dan with Barker Morisey. Ready for asphalt.
|
| 05/27/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Installing curbs and preparing final grade |
| 05/08/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Barker Morisey is preparing final grade and has removed most of the temporary fencing |
| 01/08/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Contractor is working on building installation. Material stock piles on site within construction fenced area. |
| 11/18/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Dan with Morisey construction. Concentrating on building. |
| 11/05/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Contractor working on underground utilities |
| 10/23/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Dan with Barker. Bringing in dirt to elevate pad 29 inches. Building preparations in progress.
|
| 09/19/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VFLORES1 - Contractor has started to demo parking lot.
|
| 04/09/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by RSALDAT1 - 09183, 09186, 09172, 09174, 09160. Approved |
| 04/09/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by RSALDAT1 - 09183, 09186, 09172, 09174, 09160. Approved |
| 02/05/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE CONTRACTOR WORKING ON PHASE 2 PARKING AREA NORTH OF NEW BUILDING |
| 09/18/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Contractor has installed temporary fencing and has started demo of the parking structures and native plants. |