Permit: DP19-0084

Parcel: 11615087D

Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
04/08/2021 SITE - Stormwater Follow-up BBENEDON Approved Entered by VLEON1 -
02/11/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by VLEON1 - Continued. Minor check out on private street small amounts of dirt against curb. Irrigation lines been dug. No activity on site at this time.
01/26/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by VLEON1 - CONTINUE MINOR TRACK OUT NOTED ALONG WITH DIRT ALONG CURB ON CONTINENTAL DR NO ACTIVITY ON SITE AFTER RAIN EVENT
01/22/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by VLEON1 - CONTINUE THERE ARE NO ISSUES AT THIS TIME. FINAL GRADING IN PROGRESS
01/07/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by VLEON1 - Continued. Minor track out in private drive only. No controls in place. Final grading in progress.
12/10/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by PAHUMAD1 - Continued. No issues after rain event. Silt fencing installed at West perimeter
12/03/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by PAHUMAD1 -
10/08/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by JSCHNEI2 - Continued. No issues at this time. Temporary perimeter fencing for phase 2 has been installed
10/06/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by JSCHNEI2 - Continued
09/18/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued. Trackout is contained within private drive.
09/03/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued. Material and debris stock piles remain at northwest corner of site
08/12/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by JSCHNEI2 - continued material stock piles in parking area
07/31/2020 SITE - Stormwater Follow-up BBENEDON Not ready for Inspection Entered by RSALDAT1 - Not ready. Dan with Barker Morrissey, please install storm water controls along the north west portion of the site as previously requested.
07/16/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued. No issues at this time.
06/29/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued. No issues at this time.
05/08/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued no issues
01/08/2020 SITE - Stormwater Follow-up BBENEDON Continued Entered by DMERANZ1 - No issues, check out is contained within the site.
11/18/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by DMERANZ1 - Walk to site, protections are in place. No issues at this time.
11/05/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by DMERANZ1 - I’ll track out is contained within the parking lot
10/23/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by DMERANZ1 - No issues at this time. Please schedule inspections as required.
09/19/2019 SITE - Stormwater Follow-up BBENEDON Continued Entered by VFLORES1 - There are no issues at this time. Contractor is sweeping as needed.