Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 10/23/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 10/30/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 10/29/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Complete DG installation. Complete tree staking. Install backflow assembly pad. Repair parking lot at grease interceptor. Trim out exterior clean out. Schedule inspection for both permits when ready. |
| 10/25/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Engineering has no issues that would prevent a temporary certificate of occupancy. Complete the Work shown on the development package permit, including parking stops, depressed landscape area near the dumpster, ground coverings. |
| 10/22/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by KROBLES1 - Not ready. Walk the site with a general contractor and discussed requirements for temporary certificate and for completion of the project. |