Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP18-0301
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2020 | SITE - Stormwater Follow-up | Rledonne | Approved | Entered by RLEDONN1 - |
09/09/2020 | SITE - Stormwater Follow-up | RLEDONNE | Continued | Entered by JSCHNEI2 - Continue. Walks site with superintendent went over corrections that need to be made on site. |
04/29/2020 | SITE - Stormwater Follow-up | RLEDONNE | Continued | Entered by RSALDAT1 - NO CONCERNS |
04/08/2020 | SITE - Stormwater Follow-up | RLEDONNE | Continued | Entered by RSALDAT1 - CONTROLS NEED T BE ADDED TO ON SITE CONCRETE MIX PLANT. |
02/26/2020 | SITE - Stormwater Follow-up | RLEDONNE | Continued | Entered by SFLORES2 - No concerns at this time. |
02/11/2020 | SITE - Stormwater Follow-up | RLEDONNE | Continued | Entered by DMERANZ1 - Making repairs to stormwater controls on east and west side of site. |
10/29/2019 | SITE - Stormwater Follow-up | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Stop by to see general contractor about calling in every two weeks for inspections. |