Permit: DP18-0282

Parcel: 11310001A


Addresses:

1545 E COPPER ST


Inspection Status: Passed

Inspection History: PDSD Engineering Division Pre-Construction SITE

Permit Number - DP18-0282

Inspection Description - PDSD Engineering Division Pre-Construction SITE

Inspection Status - Passed

Date Description Inspector Results Comments
12/04/2020 PDSD Engineering Division Pre-Construction SITE BBENEDON Approved Entered by PAHUMAD1 - Approved. Project manager Matt at 904-2219 has taken over this project and will schedule inspections from his development package permit. Project is nearing completion. Work Starting in right of way. Provide right of way department of transportation inspections as required
03/21/2019 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by CBELL1 - left open for informationally. Bob was diversified at 488-2418. Provide site address. SWPPP NoI has been posted. Controls have been installed. Call for intermediate inspection for all below grade storm drainage piping and bubblers at time of installation. There is no dumpster enclosure. Call for stormwater follow up inspections every two weeks.
02/26/2019 PDSD Engineering Division Pre-Construction SITE BBENEDON Not ready for Inspection Entered by CBELL1 - Bob with diversified 488-2418 will schedule a preconstruction meeting when he is able to be on site and provide city approved plans for inspection.