Permit: DP18-0280

Parcel: Unknown


Addresses:

6432 E SPEEDWAY BL

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
03/03/2020 ENGR Grading Final RLEDONNE Approved Entered by SFLORES2 -
03/03/2020 ENGR Grading Final RLEDONNE Approved Entered by SFLORES2 -
02/19/2020 ENGR Grading Final RLEDONNE Not ready for Inspection Entered by DMERANZ1 - Complete work before calling for inspection.
02/18/2020 ENGR Grading Final RLEDONNE Not ready for Inspection Entered by DMERANZ1 - Work not complete and trashing closure.
02/11/2020 ENGR Grading Final RLEDONNE Continued Entered by DMERANZ1 - Rebar for walls in trashing closure OK for grouting.
02/10/2020 ENGR Grading Final RLEDONNE Continued Entered by DMERANZ1 - Provide vertical rebar in trashing closure Past bond beam provide clean out.
02/05/2020 ENGR Grading Final RLEDONNE Continued Entered by DMERANZ1 - Footer for trash enclosure rebar OK.
06/19/2020 ENGR Grading Final DROBERTS Approved Entered by RSALDAT1 - IS APPROVED
06/12/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Met on site with GC grading contractor and asphalt contractor about vertical curbs not per approve plans. At 6 inch reveal. Talked with Steve Shields he said he would except a minimum of close to 5 inches.Per email.
06/12/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Met on site with GC grading contractor and asphalt contractor about vertical curbs not per approve plans. Talked about options waiting for Response from Steve shields. Or John Van Winkle.
06/02/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Walk site with GC vertical curbs in some parking areas under 6 inches. Provide revisions for all changes to grading and drainage. Minimum 6 inch reveal on curbs in parking area per plan.
06/02/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Walk site with GC vertical curbs in some parking areas under 6 inches. Provide revisions for all changes to grading and drainage. Minimum 6 inch reveal on curbs in parking area per plan.
05/27/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. No grading activity at this time working on building.
07/08/2020 ENGR Grading Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.
07/08/2020 ENGR Grading Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.
07/30/2021 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - Continued. Note, inspector recommends changing status to final for this expired permit as all inspections were approved at time of construction
07/08/2020 ENGR Grading Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.
07/08/2020 ENGR Grading Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.