Permit: DP18-0152

Parcel: 12501010B


Addresses:

2604 E SPEEDWAY BL

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
04/11/2019 ENGR Grading Final BBENEDON Approved Entered by CBELL1 -
06/25/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 -
06/21/2019 ENGR Grading Final BBENEDON Denied Entered by DMERANZ1 - Bollards are only in 18 inches below Finished floor. Bollards are required to be installed in 3 foot deep by 12 inch wide footings as shown detail 601.
06/11/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - Trash enclosure block walls installed as shown on page AC3 and ST4 and in compliance the city of Tucson standard detail 601. OK for grout.
05/29/2019 ENGR Grading Final DROBERTS Partial Approval Entered by DMERANZ1 - FOR THE FIRST COURSE OF THE TRASH ENCLOSURE ONLY. ALL OTHER WALLS STILL NEED TO BE INSPECTED BY THE BUILDING INSPECTOR PER THE WALL PERMIT.
05/09/2019 ENGR Grading Final BBENEDON Partial Approval Entered by VFLORES1 - Trashing closure footings. I informed Jay that vertical steel is required 32 inches.
08/06/2019 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
08/06/2019 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/23/2019 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Menu board footings.
07/23/2019 ENGR Grading Final BBENEDON Denied Entered by DMERANZ1 - Depress water harvesting area 4 as shown on your water harvesting plan, And as noted on your grading and landscaping plans.
07/12/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - I walk the site with Jay the superintendent. Water harvesting plan shows a 9 inch depression, however the sidewalk elevation is much lower than curb opening, I suggested splitting the difference and providing a swale throughout the landscape area as shown. Installing curbs and forming for sidewalks, I reminded the installer to maintain less than a 2 percent Cross slope
06/28/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Ron and I met with Jay to discuss accessible path requirements and plans 4 foot sidewalk is required 5 foot is outside of curb at the drive-through and walkways are minimum 2 1/2 feet behind curb at accessible parking spaces with no stops
06/25/2019 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Bollard installation not ready at 10:45 AM. Contractor said he’ll be ready in a few hours. 1:15 PM. Bollards and enclosure slab ready for concrete
06/11/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - Trash enclosure block walls installed as shown on page AC3 and ST4 and in compliance the city of Tucson standard detail 601. OK for grout.
05/09/2019 ENGR Grading Final BBENEDON Continued Entered by VFLORES1 - Contractor is running site utilities and Plumbing to trash enclosure area
04/22/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Site utility work in progress
04/15/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Contractor plans to pour sidewalks later this week
04/11/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Superintendent Jay had some questions about work required on the DP. He is in the process of pouring curbs and sidewalks in the right of way, I instructed him to contact his right of way Inspector.
03/08/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - contractor has installed the forms for the Building foundation