Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/11/2019 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by CBELL1 - |
| 06/25/2019 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 06/21/2019 |
ENGR Grading Final |
BBENEDON |
Denied |
Entered by DMERANZ1 - Bollards are only in 18 inches below Finished floor. Bollards are required to be installed in 3 foot deep by 12 inch wide footings as shown detail 601. |
| 06/11/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by CBELL1 - Trash enclosure block walls installed as shown on page AC3 and ST4 and in compliance the city of Tucson standard detail 601. OK for grout. |
| 05/29/2019 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by DMERANZ1 - FOR THE FIRST COURSE OF THE TRASH ENCLOSURE ONLY. ALL OTHER WALLS STILL NEED TO BE INSPECTED BY THE BUILDING INSPECTOR PER THE WALL PERMIT. |
| 05/09/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VFLORES1 - Trashing closure footings. I informed Jay that vertical steel is required 32 inches. |
| 08/06/2019 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 08/06/2019 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 07/23/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Menu board footings. |
| 07/23/2019 |
ENGR Grading Final |
BBENEDON |
Denied |
Entered by DMERANZ1 - Depress water harvesting area 4 as shown on your water harvesting plan, And as noted on your grading and landscaping plans. |
| 07/12/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - I walk the site with Jay the superintendent. Water harvesting plan shows a 9 inch depression, however the sidewalk elevation is much lower than curb opening, I suggested splitting the difference and providing a swale throughout the landscape area as shown.
Installing curbs and forming for sidewalks, I reminded the installer to maintain less than a 2 percent Cross slope |
| 06/28/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Ron and I met with Jay to discuss accessible path requirements and plans
4 foot sidewalk is required 5 foot is outside of curb at the drive-through and walkways are minimum 2 1/2 feet behind curb at accessible parking spaces with no stops |
| 06/25/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Bollard installation not ready at 10:45 AM. Contractor said he’ll be ready in a few hours.
1:15 PM. Bollards and enclosure slab ready for concrete |
| 06/11/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by CBELL1 - Trash enclosure block walls installed as shown on page AC3 and ST4 and in compliance the city of Tucson standard detail 601. OK for grout. |
| 05/09/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VFLORES1 - Contractor is running site utilities and Plumbing to trash enclosure area |
| 04/22/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - Site utility work in progress |
| 04/15/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - Contractor plans to pour sidewalks later this week |
| 04/11/2019 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by CBELL1 - Superintendent Jay had some questions about work required on the DP. He is in the process of pouring curbs and sidewalks in the right of way, I instructed him to contact his right of way Inspector. |
| 03/08/2019 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by CBELL1 - contractor has installed the forms for the Building foundation |