Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP17-0301
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/03/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
07/03/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
07/03/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
10/10/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
07/29/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DMERANZ1 - A TCO FOR THIS SITE IS OK PENDING THE APPROVAL OF BUILDING AND THE FIRE INSPECTIONS. THE FOLLOWING AREAS ARE STILL BEING WORKED ON AT THIS TIME. FOR THE TCO THERE ARE CONCERNS THAT THE ON GOING WORK MIGHT CAUSE SOME SAFETY ISSUES FOR PEDESTRIAN TRAFFIC IN THIS AREA. THERE MAY BE A NEED FOR PEDESTRIAN TUNNELS AROUND SOME OF THE BELOW MENTIONED WORK ZONES. 1) CREWS CONTINUE TO WORK ON THE AT GRADE SIDEWALK AND HARDSCAPE ON THE EAST, WEST, AND NORTH SIDES OF THIS SITE. 2). OVERHEAD STEEL AND WALL CONSTRUCTION STILL ONGOING IN THE ABOVE NOTED AREAS. THESE AREAS WILL EITHER NEED TO BE SEPARATED FROM THE PEDESTRIAN TRAFFIC ADJACENT TOO OR BELOW IF THEY ARE LOOKING FOR A TCO ON THIS SITE. 3) COMPLETE ALL LANDSCAPING AND HARDSCAPE PRIOR TO REQUESTING FOR A FULL CERTIFICATE OF OCCUPANCY FOR THIS SITE |
07/26/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by YLEON1 - NEEDS REINSPECTION. |
06/20/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS STILL WORKING ON THE LOWER PORTION OF THIS SITE, THIS WILL BE RECHECKED IN 2 WEEKS. |
06/05/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THE CONTRACTOR HAS PLACED STORM WATER CONTROLS AROUND THE SITE EVEN THOUGH THEY ARE LESS THAN AN ACRE. THEY HAVE A TRACKOUT AREA LOCATED ON THE NORTH SIDE OF THE SITE LEADING OUT ONTO SPEEDWAY BLVD. THEY HAVE CONCRETE WASHOUT BINS ON THIS SITE THAT ARE BEING UTILIZED. I HAVE ADVISED THEM THAT THEY HAVE SOME AREAS WHERE THE CONCRETE HAS OVER FLOWED FROM THE BINS AND IS IN DIRECT CONTACT WITH THE SOIL, THESE AREAS NEED TO BE CLEANED UP BY MY NEXT VISIT. CURRENTLY THE CREWS AR WORKING ON THE EXCAVTING FOR THE BELOW GRADE WALLS AND FOOTERS, AND THE POURING OF THE CONCRETE FOR THESE SAME AREAS. THEY ARE ALSO HAULING OFF EXCESS SPOIL MATERIAL FROM THIS SITE, BUT THIS IS A SLOW PROCESS DUE TO THE LACK OF HAUL TRUCKS. I HAVE REMINDED THEM THAT THEY NEED TO CONTROL ALL MATERIAL LEAVING THE SITE, AND ENSURE THAT NONE OF IT IS FALLING WITHIN THE LOCAL RIGHTS OF WAY. |