Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Approved |
Entered by RLEDONN1 - |
| 10/17/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 09/07/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 08/20/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 07/25/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 07/23/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS. |
| 07/10/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 06/21/2018 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - PROVIDE AP SWPPP PLANS ON SITE FOR INSPECTION. |
| 03/28/2018 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 02/28/2018 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - REMOVE SOIL FROM WADDLE ALONG SOUTH SIDE OF PROJECT |